SPP Regions tender model: Renovation of St. Cyril and Methodius school
The tender's subject is the St. Cyril and Methodius school renovation in Gabrovo. The tender used a Performance/Output Based Specification approach for minimum energy efficiency - class B (according to Bulgarian legislation) and is the first tender in Bulgaria to specify achievement of a minimum energy class.
SPP Regions tender model: Facilitation of energy saving habits in municipal facilities
Granollers City Council call for tender aims to procure a service contract for technical support in regards to the development of an energy strategy for municipal facilities.
SPP Regions tender model: Installation of biomass boiler using local fuel in Dosrius
The Catalan municipality of Dosrius awarded a contract in 2016 for the installation and maintenance of a biomass boiler and heat network for a school and sports facility.
SPP Regions tender model: Energy neutral primary school in Lansingerland
The contract awarded by the municipality of Lansingerland in the Netherlands in July 2017 aimed at building an energy-neutral school building. The preparation and tendering of construction and maintenance contract will be completed in 2018.
SPP Regions tender model: Energy renovation of technical installations in Egedal municipality
With this tender, Egedal Municipality has chosen to designate a consultant to schedule and manage the work on the 71 energy renovations; including design of sub-projects, implementation of main contract and consultancy in the execution phase.
SPP Regions tender model: Installation of a Heat Network in Bristol
Bristol City Council developed a district heat network linking two small networks, including the installation of a biomass boiler and efficient gas boilers.
SPP Regions tender model: Procurement of Dutch green electricity in Lansingerland
The Municipality of Lansingerland in the Netherlands awarded a 2 year contract in 2017 for the supply of 100% green electricity, deriving solely from Dutch wind, solar and biomass sources.
Bristol City Council procured a new active wood drying system solution to improve biomass boiler efficiency linked to authority's plant nursery operation.